Renault Clio: Pump assembly reservoir: Removal - Refitting
K9K, and JA5

REMOVAL
I - REMOVAL PREPARATION OPERATION
IMPORTANT
Before any operation on the sequential system,
discharge the accumulator using the Diagnostic
tool.
- To discharge the accumulator, run command
" Discharge pressure accumulator " AC081.
To confirm the pressure drop, read the " Hydraulic
pressure " parameter for the resulting value.
If there is still pressure in the accumulator, re-run the
" Discharge pressure accumulator " command until
the pressure is negligible and will not pose a risk
when the high pressure pipes are removed.
The pressure reading must be close to zero.
- Position the vehicle on a two-post lift (see Vehicle:
Towing and lifting) (MR 392, 02A, Lifting equipment).
- Remove the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
II - OPERATION FOR REMOVAL OF PART
CONCERNED

- Remove:
- the bolts (1) from the pump assembly reservoir,
- the reservoir (2) from the pump assembly.
REFITTING
I - REFITTING OPERATION FOR PART
CONCERNED
- Refit:
- the pump assembly reservoir,
- the pump assembly reservoir bolts.
- Torque tighten the pump assembly reservoir bolts
(10 Nm).
II - FINAL OPERATION.
- Refit the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
D4F, and JA3

REMOVAL
I - REMOVAL PREPARATION OPERATION
IMPORTANT
Before any operation on the sequential system,
discharge the accumulator using the Diagnostic
tool.
- To discharge the accumulator, run command
" Discharge pressure accumulator " AC081.
To confirm the pressure drop, read the " Hydraulic
pressure " parameter for the resulting value.
If there is still pressure in the accumulator, re-run the
" Discharge pressure accumulator " command until
the pressure is negligible and will not pose a risk
when the high pressure pipes are removed.
The pressure reading must be close to zero.
- Position the vehicle on a two-post lift (see Vehicle:
Towing and lifting) (MR 392, 02A, Lifting equipment).
- Remove the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
II - OPERATION FOR REMOVAL OF PART
CONCERNED

- Remove:
- the bolts (1) from the pump assembly reservoir,
- the reservoir (2) from the pump assembly.
REFITTING
I - REFITTING OPERATION FOR PART
CONCERNED
- Refit:
- the pump assembly reservoir,
- the pump assembly reservoir bolts.
- Torque tighten the pump assembly reservoir bolts
(10 Nm).
II - FINAL OPERATION.
- Refit the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
READ NEXT:
K9K, and JA5
REMOVAL
I - REMOVAL PREPARATION OPERATION
Note:
When replacing the electric pump assembly,
always replace the control relay.
IMPORTANT
Before any operation on the sequential system,
disc
K9K, and JA5
REMOVAL
I - REMOVAL PREPARATION OPERATION
Note:
When replacing the electric pump assembly,
always replace the control relay.
IMPORTANT
Before any operation on the sequential system,
disc
K9K, and JA5
REMOVAL
I - REMOVAL PREPARATION OPERATION
Note:
Before removing the solenoid valves, always
mark their respective connectors in order not to
mix them up.
IMPORTANT
Before any operation o
SEE MORE:
D4F or F4R or K4J or K4M or K9K
REMOVAL
I - REMOVAL PREPARATION OPERATION
Position the vehicle on a two-post lift (see Vehicle:
Towing and lifting) (02A, Lifting equipment).
Disconnect the battery (see ) (80A, Battery).
Remove:
the gearbox (see Manual gearbox: Removal - Refitting)
(21A, Ma
LEFT-HAND DRIVE, and AIR CONDITIONING or STANDARD HEATING
REMOVAL
I - REMOVAL PREPARATION OPERATION
Partially remove seal (1).
Remove the side panel (2).
Remove the bolt (3) from the base of the dashboard.
Unclip the trim piece (4) from the driver's side dashboard
lower cover.
Remo