Renault Clio: Pump assembly reservoir: Removal - Refitting
K9K, and JA5

REMOVAL
I - REMOVAL PREPARATION OPERATION
IMPORTANT
Before any operation on the sequential system,
discharge the accumulator using the Diagnostic
tool.
- To discharge the accumulator, run command
" Discharge pressure accumulator " AC081.
To confirm the pressure drop, read the " Hydraulic
pressure " parameter for the resulting value.
If there is still pressure in the accumulator, re-run the
" Discharge pressure accumulator " command until
the pressure is negligible and will not pose a risk
when the high pressure pipes are removed.
The pressure reading must be close to zero.
- Position the vehicle on a two-post lift (see Vehicle:
Towing and lifting) (MR 392, 02A, Lifting equipment).
- Remove the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
II - OPERATION FOR REMOVAL OF PART
CONCERNED

- Remove:
- the bolts (1) from the pump assembly reservoir,
- the reservoir (2) from the pump assembly.
REFITTING
I - REFITTING OPERATION FOR PART
CONCERNED
- Refit:
- the pump assembly reservoir,
- the pump assembly reservoir bolts.
- Torque tighten the pump assembly reservoir bolts
(10 Nm).
II - FINAL OPERATION.
- Refit the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
D4F, and JA3

REMOVAL
I - REMOVAL PREPARATION OPERATION
IMPORTANT
Before any operation on the sequential system,
discharge the accumulator using the Diagnostic
tool.
- To discharge the accumulator, run command
" Discharge pressure accumulator " AC081.
To confirm the pressure drop, read the " Hydraulic
pressure " parameter for the resulting value.
If there is still pressure in the accumulator, re-run the
" Discharge pressure accumulator " command until
the pressure is negligible and will not pose a risk
when the high pressure pipes are removed.
The pressure reading must be close to zero.
- Position the vehicle on a two-post lift (see Vehicle:
Towing and lifting) (MR 392, 02A, Lifting equipment).
- Remove the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
II - OPERATION FOR REMOVAL OF PART
CONCERNED

- Remove:
- the bolts (1) from the pump assembly reservoir,
- the reservoir (2) from the pump assembly.
REFITTING
I - REFITTING OPERATION FOR PART
CONCERNED
- Refit:
- the pump assembly reservoir,
- the pump assembly reservoir bolts.
- Torque tighten the pump assembly reservoir bolts
(10 Nm).
II - FINAL OPERATION.
- Refit the pump assembly (see 21B, Sequential
gearbox, Pump assembly: Removal - Refitting, 21B-12).
READ NEXT:
K9K, and JA5
REMOVAL
I - REMOVAL PREPARATION OPERATION
Note:
When replacing the electric pump assembly,
always replace the control relay.
IMPORTANT
Before any operation on the sequential system,
disc
K9K, and JA5
REMOVAL
I - REMOVAL PREPARATION OPERATION
Note:
When replacing the electric pump assembly,
always replace the control relay.
IMPORTANT
Before any operation on the sequential system,
disc
K9K, and JA5
REMOVAL
I - REMOVAL PREPARATION OPERATION
Note:
Before removing the solenoid valves, always
mark their respective connectors in order not to
mix them up.
IMPORTANT
Before any operation o
SEE MORE:
K9K, and 750 or 752 or 766 or 768
IMPORTANT
Before carrying out any work on the injection circuit,
check using the Diagnostic tool
that the injector rail is not under pressure,
that the fuel temperature is not too high.
It is essential to respect the safety and cleanliness
advice whenever work
F4R
REMOVAL
I - REMOVAL PREPARATION OPERATION
Disconnect the battery (see Battery: Removal - Refitting)
(MR 392, 80A, Battery).
Remove:
the throttle valve (see 12A, Fuel mixture, Throttle
valve: Removal - Refitting, 12A-33),
the intake distributor (see 12A, Fuel mixture, Inlet
distribut